Council to approve £18m increase as One Horton Heath costs top £500m

Eastleigh Borough Council will consider a fresh £18.3 million budget increase for its flagship One Horton Heath housing project next week, pushing the total projected cost of the scheme to just over £500 million.

Councillors on the Audit and Resources Committee will meet on Monday, 9 June, to scrutinise the revised budget, which includes £2.1 million for electric vehicle charging infrastructure and an additional £16.3 million to cover higher-than-expected construction and financing costs. The increased borrowing will be funded from future scheme surpluses, though no homes have yet been completed.

Project could become ‘unviable’

The report also reveals that the timeline for the 2,500-home development now stretches to 2035—but council officers warn that unless delivery is accelerated, the project will become “unviable” due to increased borrowing costs and delayed income.

One of the biggest cost increases relates to electricity supply. A new 11km cable from Velmore to Bishopstoke is now required after engineers found the Eastleigh railway bridge could not accommodate the original route. The budget for this work has jumped from £1.5 million to £5.1 million.

Meanwhile, a new footpath to Hedge End Station has hit a six-week delay after a high-pressure gas main was discovered. The additional work is expected to cost £144,000.

School funding reshuffle and marketing push

Despite these setbacks, the council is pressing ahead with plans to reallocate £20 million in developer contributions—originally earmarked in the draft s106 agreement for school provision—to directly fund the delivery of the on-site primary school. Officers argue this will allow the school to reflect the council’s design ambitions rather than a standard model from Hampshire County Council.

However, outline planning application for the full development has yet to be formally granted. Although the application was recommended for approval in March, it is still awaiting the completion of legal agreements and an Appropriate Assessment. Despite this, the council has already hired marketing staff and is preparing to launch off-plan sales this summer.

Return on investment questioned

As previously reported by Eastleigh News, the project was originally approved in 2017 with a cost of £142 million and a forecast profit of £11.8 million. The latest estimates show that by 2028, the council expects to receive just £194,000 a year in rental income from the homes—equivalent to 0.04% return on a £500 million outlay. Officers say the long-term value lies in eventual full ownership of the housing stock and other public assets.

Housing plots are currently valued at £100,000, which is lower than the estimated market sale value of £117,000. But the report warns that rising build costs and possible reductions in housing density could erode that margin.

Senior staffing remains a concern. Several key personnel have recently left the programme, while others have declined senior roles. The council is now relying on external support to maintain momentum.

Transparency and audit concerns

This latest update comes amid broader questions about Eastleigh’s financial governance. In March, Eastleigh News revealed that many properties in the council’s £560 million commercial property portfolio are worth less than the outstanding associated borrowing. In April, we also reported that whistleblower concerns over One Horton Heath had not been fully addressed, according to the council’s external auditors. The audit for the 2021–22 financial year remains incomplete.

Russ Kitching, spokesperson for Reform UK in Eastleigh, told Eastleigh News he was concerned about the level of transparency surrounding the development, “We’ve been raising the alarm about One Horton Heath for over a year. This latest report confirms our fears. The Lib Dems have gambled public money on a project that is now struggling to remain viable. Residents deserve transparency, not excuses.”

Kitching also questioned the decision to redact nine paragraphs from the public version of the report. “What is the council hiding? It’s public money and we have a right to know how our money is being spent,” he said. At the previous meeting of the Audit and Resources Committee, Kitching directly challenged councillors over the number of items being heard in exempt session.

Opposition voices speak out

In January, Fair Oak councillor Steve Broomfield, a member of the Horton Heath Development Management Committee, commented on the challenges of the scheme. “The delays and rising costs make it easy to see why private developers decided to walk away from the site,” he told Eastleigh News,

Local MP Paul Holmes, has also criticised the project in comments made to the Daily Echo, “My constituents are having to pay their share of £600 million of debt to build out this project that simply isn’t deliverable,” he said. “Repeatedly auditors have been concerned about financial practices and management, deliverability and a lack of political management by the Lib Dem administration.”

Council’s long-term commitments face future uncertainty

The council’s ongoing financial commitments also come at a time of significant uncertainty about its own future. Eastleigh Borough Council is currently under reconsideration as part of wider proposals for local government reorganisation and devolution in Hampshire. While no final decision has been made, it is widely expected that Eastleigh will be absorbed into a larger unitary authority within the next few years.

Despite this, the council continues to approve long-term financial decisions and new borrowing—such as the latest £18.3 million budget increase—with little public discussion of how reorganisation might impact the viability or accountability of major projects like One Horton Heath.

The Audit and Resources committee meeting will take place at Eastleigh House on Monday June 9 at 6.15pm.

The public are welcome to attend except during agenda Item 8 for paragraphs: 11,12,13,15,18,19,21,22,24,86, agenda item 9, agenda item 10 (One Horton each appendices) and agenda item 11 (property transaction). All the foregoing items will be held in private.